Resumen:

This paper presents a goal programming methodology for solving maintenance scheduling of thermal generating units under economic and reliability criteria. The advantages of a multicriteria approach are demonstrated by comparing the effects that costs and reliability have on each other in power plants maintenance scheduling. The problem is formulated as a large scale mixed integer programming problem implemented in the mathematical programming language GAMS and solved using OSL. Weekly maintenance scheduling of the large scale Spanish power system for a year period illustrates the proposed methodology


Palabras Clave: integer programming maintenance engineering power generation planning scheduling thermal power stations


Índice de impacto JCR y cuartil WoS: 6,500 - Q1 (2023)

Referencia DOI: DOI icon https://doi.org/10.1109/59.780915

Publicado en papel: Agosto 1999.

Publicado on-line: Agosto 1999.



Cita:
L. Muñoz-Moro, A. Ramos, Goal programming approach to maintenance scheduling of generating units in large scale power systems. IEEE Transactions on Power Systems. Vol. 14, nº. 3, pp. 1021 - 1027, Agosto 1999. [Online: Agosto 1999]


    Líneas de investigación:
  • *Planificación Táctica a Medio Plazo